Steel structure warehouse hoisting process and hoisting plan-Chapter 1

Time:[2021-9-25]  Hits:2378

Hoisting process

 

Positioning --- Calibration Height --- Column Top Bolt Embedded --- Calibration Height - Elastic Line - Column Installation - Steel Beam Installation - Secondary Structure Installation --- --Welding----Repainting----Completion

 

 

Steel column installation process


A,Lifting of steel columns

 

1.Re-test the foundation, including the exposed length of the anchor bolt, the displacement deviation of the anchor bolt center line to the reference line, the distance between the anchor bolts, and the foundation elevation. The unqualified ones can be handled before lifting.

 

2.In order to control the installation elevation of the column, a 500mm position is also marked on the visible cross section of the column in advance for fine-tuning and correction of the elevation during installation. Install the steel column on the basis of qualified retest, first tie the column with a single steel wire rope, and choose the position of the lifting point at a position 1/3 of the length of the column from the end of the column. The column is lifted by the rotation method, and the steel column is lifted and sent to the installation position. The lashing place should be padded.

 

 

B, the correction of the steel column

 

1.Draw the center line in advance on the visible surface of the column, and then use the theodolite to adjust the verticality of the column in two mutually perpendicular directions.

 

2.Control the verticality of the column by measuring the distance between the inner side of the column and the control line on the building.

 

3.The adjustment of the elevation, axis and verticality deviation of the column are related to each other, and the correction work will be completed when all the standards are met.

 

 

Steel beam installation process

 

Unload the steel beams to the vicinity of each column, hoist them to the floor with a car, and then install them by mast cranes. The main beams with some heavy components can be platform craned with car cranes. The secondary beam can be installed with a self-made wheeled crane (5t). Starting from the third zone, the main girder, the secondary girder and then the purlin, the steel girder shall be hoisted by masts one by one according to the number. Only when the two ends of the girder are fastened with bolts (or spot welded firmly), the hooks can be loosened and the others are hoisted in sequence Steel beams. Weld after passing the inspection.
The lashing and hoisting points of steel beams are particularly important. Steel poles can be used when the steel beams are too long. There are many steel beams in this project with a maximum length of about 20m. A triangular hanging plate is used to enlarge the distance between the steel ropes to increase the angle of the steel ropes. Require. Schematic diagram of steel beam lashing.

 


Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
超声波污泥界面仪| HycloneMEM液体培养基| 土壤样品干燥箱| 工业烟气分析仪| 液体微生物气溶胶采样器| 深圳高品质电源适配器| 贺德克滤芯| 批发代理| 韩国丝锥价格| 便携式光化学测氧仪| CBS液氮罐| 气象环境监测设备| 原料桶加热融化烘箱| 炉温记录仪| 出租变压器| 15ml锥形离心管| 高压曝气风机| 光电开关传感器| 内孔加工| 上海吊秤厂家| 温度传感器生产厂家| 编织网管| DGS18矿用巷道灯| vaisala维萨拉变送器| 临沂燃气热水器| 离子交换层析检测仪| 华美挤塑板| 钛棒过滤器| 粉末压片模具| 防爆温度变送器| 临沂三菱中央空调| 3NH分光测色仪| 空气能烘干机| 防倾倒开关| 大功率直流电机| 车充定位器| 制冷恒温槽| 石笼网| 企业电能管理系统| Accuri| 中央供料系统|