During the installation of steel structure, the following problems shall be paid attention to:

Time:[2021-8-28]  Hits:2335

During the installation of steel structure, the following problems shall be paid attention to:

1. Before the installation of steel structure, all members shall be comprehensively inspected, such as whether the number, length, perpendicularity of members and the size between bolt holes at installation nodes meet the design requirements; The defects generated during fabrication and deformation generated during transportation shall be corrected on the ground and properly solved.

2. The steel column and foundation are generally connected by embedded anchor bolts. Therefore, before installing the steel column, check the size between the column base bolts, whether the length exposed to the foundation surface, the elevation of the foundation top meet the design requirements, and whether the thread of the column base anchor bolt is damaged (generally, measures are taken during foundation construction to protect the column base anchor bolt and its thread from being damaged).

3. When hoisting the steel structure, proper measures shall be taken to prevent excessive bending and torsion deformation. The contact part between the rope buckle and the component shall be padded with cushion blocks to prevent the component from being damaged.

4. After the steel structure is hoisted in place, the support and other connecting members shall be fastened in time to ensure the stability of the structure.

5. The hoisting of all superstructure can only be carried out after the substructure is in place, corrected and fastened with supporting members.

6. Assemble a large installation unit on the ground according to the lifting capacity of the site installation machinery to reduce the workload of high-altitude operation.

Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
布袋除尘器厂家| 凯米尼尔搅拌机| 地埋式生活污水净化槽定制厂家| 防爆排风扇| 杰弗伦传感器| BIFOLD气控阀| 激光切割机电源| 平板式泡罩包装机| 薄壁不锈钢管| 熔体计量泵| 舌面象分析系统| 大鼠肝实质细胞| 架空线路| 全自动反冲洗过滤器| 进口碳硫分析仪| 水蒸气透过率测试仪| 多元素火焰光度计| 速冻冷库安装设计| 光伏支架成型设备| SF6智能微水测量仪| SPME固相微萃取头| 印花加工门户网站| 全自动外泌体提取浓缩仪| 除尘式糖衣机| 智能平板导热仪| 无菌水样采集袋| 上银直线导轨| 温度变送器| 管道式粉碎型格栅| 衬氟自吸泵| 冷冻修毛边机| 大量程气体流量计| 石化气体露点仪| 样品瓶(色谱样品瓶)百科| 恒温恒湿测试箱| 沸石转轮装置| 高速精密冲床| 护栏网| 超纯水机| 国际橡胶微型硬度计| 钢管高压无气喷涂机|