日韩精品一区二区三区四区蜜桃,欧美专区,亚洲AV超清无码不卡在线网络,精品成在人线AV无码免费看

Language:CHINESESENGLISH

Home > News > Analysis of key construction points of steel column and frame beam of high-rise steel structure
CONTACT US
  • Address:Pingtang Industrial District, Shipeng Village, Shishan Town, Nanhai District, Foshan City,
  • Phone:0757-81002668/0757-63323396
  • Fax:0757-81196682
  • Contact:Ben Zheng/13826981293 Kerry Lu/13751224830
  • E-mail:sbs@sbsprefabhouse.com
  • URL:http://www.hycjk.com

Analysis of key construction points of steel column and frame beam of high-rise steel structure

Time:[2021-8-25]  Hits:2108

Analysis of key construction points of steel column and frame beam of high-rise steel structure

1、 Analysis on key points of steel column construction of high-rise steel structure

Steel column is a vertical component that determines the floor height and the total height of the building, and its fabrication and processing needs to meet the corresponding specifications and standards. At the same time, the shrinkage deformation of the weld and the compression deformation caused by the vertical load need to be considered in the process of turning and blanking. Therefore, the turning and blanking length of the steel column is not equal to the design length, even if it is only a few millimeters, it can not be ignored. Moreover, when the sections of the upper and lower steel columns are completely equal, they are not allowed to be interchanged. It is required that each steel column shall be numbered differently and installed in place correctly. The welding of stiffener plate in rectangular or square steel column shall adopt nozzle electroslag welding according to the requirements of current specifications, and other forms such as opening on box plate and slot plug welding are not allowed.

2、 Analysis on key construction points of high-rise steel structure frame beam

In order to ensure that the joint area at the connection between the frame beam and the steel column has good ductility, connection reliability and floor height accuracy, during factory manufacturing, a cantilever beam (short corbel) is set at the position where the frame beam is located. The connection between the upper and lower flanges of the cantilever beam and the steel column adopts cut penetration weld, and the web adopts fillet weld. The frame beam is connected with the cantilever beam (short corbel) of the steel column, the upper and lower flanges are connected by the full penetration weld of the lining plate (also the arc striking plate), and the web is connected by high-strength bolts. Since the allowable deviation of reinforced concrete construction is far greater than the accuracy requirements of steel structure, when the frame beam is connected with reinforced concrete shear wall or reinforced concrete cylinder wall, the connecting plate of web can be opened with elliptical holes, which shall meet the requirements of hole edge distance. The blanking length of frame beam is also not equal to the design length, and the welding shrinkage deformation shall be considered. The welding shrinkage deformation can be calculated by empirical formula, and then checked according to the actual processing, so as to determine the exact length of the turning and blanking. High strength bolt connection or welding connection can be adopted for the connection of the upper and lower flanges of the frame beam. At present, most of them adopt full penetration welding connection with lining plate. During construction, the lower flange shall be welded first, and then the upper flange shall be welded. One end shall be spot welded for positioning, and then the other end shall be welded. The web is connected with high-strength bolts. It is necessary to fully understand whether friction type or pressure bearing type high-strength bolts are used in the design. The friction coefficient of friction type high-strength bolt should be selected reasonably. When using high-strength bolt group connection, the accuracy of hole position is very important. At present, template drilling and multi axis NC drilling are generally used for hole making. The former has low precision and the latter has high precision, so the latter should be given priority. When the formwork is used to make holes, the accuracy of the formwork shall be ensured to ensure the accuracy requirements of the assembly holes of high-strength bolts and site installation holes. In case of local deviation of hole position, reaming with reamer is only allowed. It is strictly prohibited to use gas cutting for hole expansion. If gas cutting is used for hole expansion, it shall be handled as a major quality accident.

Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
柴油机水泵机组| KIT便携式土壤水分仪| 酵母抽提物喷雾干燥机| 土壤酸碱度计| 上海家君真空仪表| 多年热熔钻设备研发制造经验| 中山振动盘| 超耐压单芯过滤器| 乳化液浓度传感器| 超声波设备清洗机| 浮漂在线监测仪| 山东40Cr大口径合金管| 机械格栅设备| 制样自动切割机| 通孔增量编码器| 中央电热水器| KANON扭力起子| 不锈钢套筒阀| 智能制丸机| 水处理石英砂滤料颗粒| 程控工频耐压试验装置| 电缆故障测试仪[精准定位]| 温室喷灌机生产厂家| ANSI455GMP认证| 全自动丝网印刷机| 个人辐射监测仪| 陶瓷注水阀| 砂带拉丝机| 插入式靶式流量计| 曲面小孔光泽度仪| 超低温液氮深冷箱| 半导体推拉力测试机| 口服液洗烘灌轧机| 国产网络分析仪| 二级智能生物安全柜| 川仪液位开关| sbs改性沥青| 双波段闪烁仪| GPS北斗同步时钟| 锰钢轧花网| 软化水耗材|